PLACEMENT: Consent
TITLE:
title
ADOPTION OF A RESOLUTION APPROVING AND ACCEPTING 27 PERPETUAL EASEMENTS ALONG NE OCEAN BOULEVARD AND NE MACARTHUR BOULEVARD IN JENSEN BEACH TO REPLACE THE CURRENT 50-YEAR EASEMENTS
end
EXECUTIVE SUMMARY:
executive summary
This is a request for the adoption of a Resolution approving and accepting 27 Perpetual Easements from property owners along NE Ocean Boulevard and NE MacArthur Boulevard for the 4-mile beach renourishment project.
body
DEPARTMENT: Public Works
PREPARED BY: Name: Carla T. Segura, FRP
Title: Real Property Manager
REQUESTED BY: John Maehl, Environmental Resources Administrator
PRESET:
PROCEDURES: None
BACKGROUND/RELATED STRATEGIC GOAL:
1. Perpetual Easement drafted by:
Martin County
2. Parties to the Agreement/Contract:
Property Owner(s), Grantor(s)
Martin County, Grantee
3. Purpose of the Agreement/Contract:
To continue maintaining the dunes along the coastline and beaches on Hutchinson Island
4. New/Renewal/Modification:
New
5. Duration:
Perpetual
6. Benefits to Martin County:
Additional shoreline projection along Martin County's shoreline from the St. Lucie County line to Indian River Plantation
7. Cost to Martin County:
Minimal recording costs
In August of 1995, the Federal Beach Project was approved authorized as a 3.75-mile project beginning at the northern Martin County line and continuing south to the Dunes Club Condos along NE Macarthur Blvd. The construction took place from December 1995 to April 1996 with a County funded 1/4 mile "local option" added to the south end, resulting in the full 4-mile-long project.
Since that time a total of 6 projects have been constructed including 2 partial projects (2001, 2002) and post hurricane (recovery) projects in 2005, 2013 and 2018. Material for the first 4 projects came from Gilbert shoal, which lies approximately 1.2 miles off the southern project limit and was pumped directly to the ...
Click here for full text