File #: 26-0507   
Type: Consent Status: Agenda Ready
In control: Board of County Commissioners
On agenda: 2/10/2026 Final action:
Title: INTERLOCAL AGREEMENT FOR THE SOUTH SEWALL'S POINT FORCE MAIN EXTENSION PROJECT PHASE 3
Attachments: 1. 2026_0106 Interlocal Agreement South Sewall's Point Phase 3 - TOSP Executed.pdf

PLACEMENT: Consent

TITLE:

title  

INTERLOCAL AGREEMENT FOR THE SOUTH SEWALL’S POINT FORCE MAIN EXTENSION PROJECT PHASE 3

end

EXECUTIVE SUMMARY:

executive summary

The Board of County Commissioners is requested to authorize execution of the Interlocal Agreement between Martin County and the Town of Sewall’s Point for the South Sewall’s Point Force Main Extension.

body

DEPARTMENT: Utilities and Solid Waste                     

PREPARED BY:                      Name: Leo Repetti, P.E.                     

                     Title:                     Technical Services Administrator                     

REQUESTED BY: Samuel Amerson, P.E., Utilities & Solid Waste Director                                          

 

PRESET:     

PROCEDURES: None                     

 

BACKGROUND/RELATED STRATEGIC GOAL:

 

1.                     Agreement prepared by:

Martin County (Legal Department)

 

2.                     Parties to the Agreement:

Martin County

                     The Town of Sewall’s Point

 

3.                     Purpose of the Agreement:

To provide a mechanism for transfer of the infrastructure to Martin County for maintenance and operation once complete.

 

4.                     New/Revised Document:  New

 

5.                     Duration:

Until final completion of the Project and turnover of the infrastructure is complete.

 

6.                     Benefits to Martin County:

The wastewater force mains installed as part of the Project will provide service availability to approximately 205 Martin County Residents.

 

7.                     Costs to Martin County:  $0

 

The Town of Sewall’s Point (Town) has budgeted for the design, permitting and construction, including installation, of small diameter force mains, gravity sewer and a lift station to provide sanitary sewer service to properties within its boundaries, that will connect to the Martin County’s utility service (Town Project).

 

The Town has obtained bids, utilizing a unit price and quantity document and contract for goods and services required for the construction of the Project, and has selected and contracted the Construction Engineering and Inspection (CEI) for the Project.

 

The Town approved the item on their January 6, 2026 regular Town Commission meeting.

 

ISSUES:

 

None

 

LEGAL SUFFICIENCY REVIEW:

 

This item has been reviewed for legal sufficiency to determine whether it is consistent with applicable law, has identified and addressed legal risks, and has developed strategies for legal defensibility. 

 

RECOMMENDED ACTION:

 

RECOMMENDATION

Move that the Board authorize the Chair to execute the Interlocal Agreement for the South Sewall’s Point Force Main Extension Project.

 

ALTERNATIVE RECOMMENDATIONS

Pull this item from the Consent Agenda and provide additional direction to staff. 

 

FISCAL IMPACT:

 

RECOMMENDATION

None

                     

ALTERNATIVE RECOMMENDATIONS

None

 

DOCUMENT(S) REQUIRING ACTION:

Budget Transfer / Amendment                      Chair Letter                                                               Contract / Agreement

Grant / Application                                          Notice          Ordinance                     Resolution

Other: