Title: RESOLUTION ADOPTING AND IMPLEMENTING THE WESTERN CORRIDOR WATER & SEWER EXTENSION PROJECT FISCAL SUSTAINABILITY PLAN AS REQUIRED BY STATE REVOLVING FUND CLEAN LOAN AGREEMENT WW430250
Attachments: 1. Resolution Approving Fiscal Sustainability Plan for Western Extension SRF Loan Agreemen CW43025.pdf, 2. Western Corridor Fiscal Sustainability Plan.pdf, 3. 1_Martin County WW430250 Contract Signed.pdf

PLACEMENT: Consent

TITLE:

title  

RESOLUTION ADOPTING AND IMPLEMENTING THE WESTERN CORRIDOR WATER & SEWER EXTENSION PROJECT FISCAL SUSTAINABILITY PLAN AS REQUIRED BY STATE REVOLVING FUND CLEAN LOAN AGREEMENT WW430250

end

EXECUTIVE SUMMARY:

executive summary

Board action is requested to adopt a resolution to implement the Western Corridor Water & Sewer Extension Project Fiscal Sustainability Plan as required by Section 8.12 of the Florida State Revolving Fund Loan Agreement WW430250.

body

DEPARTMENT: Utilities and Solid Waste                     

PREPARED BY:                      Name: Leo Repetti                     

                     Title:                     Technical Services Administrator                     

REQUESTED BY: Samuel Amerson, P.E., Utilities & Solid Waste Director                                          

 

PRESET:     

PROCEDURES: None                     

 

BACKGROUND/RELATED STRATEGIC GOAL:

 

The Western Corridor Water & Sewer Extension Project is complete and all disbursements from the Florida State Revolving Fund Loan program have been received.  In order to close on the Loan as required by section 8.12 of the WW430250 Loan Agreement, the Board is required to adopt by Resolution a Fiscal Sustainability Plan.

 

The Fiscal Sustainability Plan and associated Asset Inventory List are attached.

 

ISSUES:

 

None

 

LEGAL SUFFICIENCY REVIEW:

 

This item has been reviewed for legal sufficiency to determine whether it is consistent with applicable law, has identified and addressed legal risks, and has developed strategies for legal defensibility. 

 

RECOMMENDED ACTION:

 

RECOMMENDATION

Move that the Board adopt the Resolution to implement the Western Corridor Water & Sewer Extension Project Fiscal Sustainability Plan as required by Section 8.12 of the Florida State Revolving Fund Loan Agreement WW430250.

 

ALTERNATIVE RECOMMENDATIONS

Pull this item from the Consent Agenda and direct staff accordingly.

 

FISCAL IMPACT:

 

RECOMMENDATION

None, as the costs associated with maintenance and repair of the identified assets is covered by the Utilities Department operating revenues.

                     

ALTERNATIVE RECOMMENDATIONS

None

 

DOCUMENT(S) REQUIRING ACTION:

Budget Transfer / Amendment                      Chair Letter                                                               Contract / Agreement

Grant / Application                                          Notice          Ordinance                     Resolution

Other: