PLACEMENT: Consent
TITLE:
title
ADOPTION OF A RESOLUTION APPROVING AND ACCEPTING A MODIFICATION OF RIGHT-OF-WAY EASEMENT FROM THE SCHOOL BOARD OF MARTIN COUNTY ALONG SW BULLDOG WAY IN STUART
end
EXECUTIVE SUMMARY:
executive summary
This is a request for the adoption of a Resolution approving a Modification of Right-of-Way Easement (Modification) with the School Board of Martin County (SBMC). The Board of County Commissioners (BOCC) adopted Resolution No. 25-11.17, on November 18, 2025, approving a Right-of-Way Easement (Easement) along SW Bulldog Way, supporting a Transportation Alternatives Program (TAP) project. The Modification is necessary to add additional right-of-way to the current Easement area.
body
DEPARTMENT: Public Works
PREPARED BY: Name: Carla T. Segura, FRP
Title: Real Property Manager
REQUESTED BY: Kathryn Durno, Grants Coordinator, Capital Projects
PRESET:
PROCEDURES: None
BACKGROUND/RELATED STRATEGIC GOAL:
1. Modification Easement Prepared By:
Martin County
2. Parties to the Modification Easement:
School Board of Martin County - Grantor
Martin County - Grantee
3. Purpose of the Modification Easement:
Modify the area currently approved for easement
4. New/Renewal/Modified:
Modified
5. Duration:
Perpetual
6. Benefits to Martin County:
Provide the extra space needed for the development of a sidewalk for South Fork High School
7. Cost to Martin County:
Minimal recording fees
On November 18, 2025, the BOCC adopted Resolution 25-11.17 accepting an Easement, recorded in Official Records Book 3536, Page 515, Public Records of Martin County, Florida, from the SBMC, along SW Bulldog Way in Stuart for a Florida Department of Transportation ("FDOT") TAP project grant.
The original sketch and legal description of the Easement area showed the Easement running along the back of the curb of SW Bulldog Way. After further review and finalizing the design, it was noted that in order to make all the necessary improvements, the ...