Martin County

File #: 24-0126   
Type: Public Hearing Quasi Judicial Status: Passed
In control: Board of County Commissioners
On agenda: 11/7/2023 Final action: 11/7/2023
Title: REQUEST BY FLORIDA POWER AND LIGHT COMPANY FOR MAJOR FINAL SITE PLAN APPROVAL FOR THE FAWN SOLAR FACILITY PROJECT (F110-004)
Attachments: 1. 2023_1016_F110-004_DRT_STAFF_FINAL.pdf, 2. 2023_0922_F110-004_RESO_APPR.pdf, 3. 2023_1013_F110-004 FSP EXHIBIT B.pdf, 4. 2023_0922_F110-004_APP.pdf, 5. 2023_1018_F110-004_LAD_Tearsheet.PDF, 6. 2023_1013_F110-004 SAMPLE LETTER.pdf, 7. 2023_1013_F110-004 PROPERTY OWNER CERT, 8. 2023_1019_F110-004 Sign Certifcation.pdf, 9. Presentation, 10. 2023_0922_F110-004_RESO_DENY.pdf
PLACEMENT: Public Hearings - Quasi-Judicial
TITLE:
title
REQUEST BY FLORIDA POWER AND LIGHT COMPANY FOR MAJOR FINAL SITE PLAN APPROVAL FOR THE FAWN SOLAR FACILITY PROJECT (F110-004)
end
EXECUTIVE SUMMARY:
executive summary
This is a request for approval of a major final site plan for the development of an unmanned 74.5 MW solar energy facility on approximately 600 acres of agricultural land. The proposed development is located along the north side of SW Citrus Boulevard at 16364 SW Citrus Boulevard in Palm City. The proposed project is approximately 4.7 miles east of the intersection of SW Warfield Boulevard. Included with this application is a request for a Certificate of Public Facilities Reservation.
body
DEPARTMENT: Growth Management
PREPARED BY: Name: Brian Elam, PMP
Title: Principal Planner
REQUESTED BY: Culpepper & Terpening, Inc., Dennis Murphy, Principal Planner

PRESET:
PROCEDURES: Quasi-Judicial

BACKGROUND/RELATED STRATEGIC GOAL:

This is a request by Culpepper & Terpening, Inc., on behalf of FPL Company for approval of a major final site plan for the FPL Fawn Solar Generation Site. The proposed development includes an unmanned 74.5-megawatt solar energy facility and associated infrastructure on an approximate 600-acres of agricultural land currently being used as a pepper farm. The project site is located approximately 5 miles east of the Village of Indiantown and south of the existing FPL White Tail Solar Energy Center.

The proposed FPL Fawn Solar Generation Site is a solar energy facility. Solar farms are a permitted use in the A-2, Agricultural District subject to the requirements defined in section 3.100.1 of the Land Development Regulations, Martin County Code.

This item has been scheduled for consideration by the Local Planning Agency (LPA) on November 2, 2023. The LPA's recommendation will be provided to the Board of County Commissioners.

The following supporting materials are provided attached to this agenda item.
S...

Click here for full text