PLACEMENT: Public Hearings
TITLE:
title
PUBLIC HEARING AND FINAL ASSESSMENT RESOLUTION FOR THE S.E. FLAMINGO DRIVE/S.E. KARIN STREET MUNICIPAL SERVICE BENEFIT UNIT
end
EXECUTIVE SUMMARY:
executive summary
The Board of County Commissioners is requested to hold a public hearing and adopt the Final Assessment Resolution for the S.E. Flamingo Drive and S.E. Karin Street Municipal Service Benefit Unit to allow a road paving project and to certify the special assessment roll to the Tax Collector.
body
DEPARTMENT: Public Works
PREPARED BY: Name: George Dzama, P.E.
Title: Capital Projects Manager
REQUESTED BY: S.E. Flamingo Drive Property Owners
PRESET:
PROCEDURES: None
BACKGROUND/RELATED STRATEGIC GOAL:
The Public Works Department is in receipt of a majority ballot vote from the property owners adjacent to S.E. Flamingo Drive for Martin County (County) to pave and perpetually maintain 595 feet of S.E. Flamingo Drive from S.E. Duncan Street to its north end near the Eaglewood Golf and Tennis Community. S.E. Flamingo Drive is an open public road located in Hobe Sound, Florida that is currently privately maintained. There are seven properties in the proposed project area.
The affected property owners in this project area were sent ballots indicating that the estimated cost of the project would be between $16,015 and $19,991.50 per property. The final tally of all the ballots received to date as verified by the Martin County Supervisor of Elections office indicate 5 properties FOR the project, 0 AGAINST and 2 that did not vote.
On July 10, 2018, the Board of County Commissioners (Board) adopted the Initial Assessment Resolution #18-7.4 for the S.E. Flamingo Drive and S.E. Karin Street Municipal Service Benefit Unit.
Based on the final design and County contribution made, the initial prepayment amount is $13,872.14 per parcel unit (single family dwelling unit equivalent) which is below the estimated range as outlined in the ballots mentioned ...