Martin County

File #: 19-0076   
Type: Departmental Status: Agenda Ready
In control: Board of County Commissioners
On agenda: 11/20/2018 Final action:
Title: SEPTIC TO SEWER PROGRAM UPDATE
Attachments: 1. Septic to Sewer Update BOCC November 20 2018_Revised NOV 06.pdf

PLACEMENT: Departmental

TITLE:

title  

SEPTIC TO SEWER PROGRAM UPDATE

end

EXECUTIVE SUMMARY:

executive summary

Staff is prepared to update the Board on the Septic to Sewer Program and present additional initiatives for Board consideration.

body

DEPARTMENT: Utilities and Solid Waste                     

PREPARED BY:                      Name: Samuel Amerson, P.E.                     

                     Title:                     Utilities & Solid Waste Director                     

REQUESTED BY: Board of County Commissioners                                          

 

PRESET:     

PROCEDURES: None                     

 

BACKGROUND/RELATED STRATEGIC GOAL:

 

The Board has identified septic to sewer conversions as a priority necessary to our environmental goals.  The intent of this presentation is to outline the steps necessary to create a viable path forward in meeting this objective.  Staff is pleased to provide an update on the current initiatives designed to accelerate the opportunity for septic to sewer conversions within the utility service area.  These include the Septic to Sewer Program, several Vacuum Assisted Gravity Sewer Projects underway, and a proposed “Connect to Protect” Grinder Sewer System initiative. 

A critical part of our analysis includes an estimate of the level of financial support required to establish and maintain a consistent special assessment charge throughout the various project areas.  Staff will also present, for the Board of County Commissioners’ (Board) consideration, policy recommendations that are intended to encourage early connection to the sewer systems by providing financial discounts and favorable payment plan.

 

ISSUES:

 

A complete analysis of the options available for sewer conversion projects was presented at the November 3, 2015 meeting (see Table 6).  The list of projects identified the most cost efficient project type.  The least cost option for the 24 projects totaled $138M and the average cost per parcel estimate was $15,151.00 in 2015.

 

 

 

                     

                                          

 

Utilities and Solid Waste staff, at the Board’s request, presented a prioritized list of septic to sewer projects at the March 29, 2016 meeting.  The six neighborhoods listed totaled an estimated construction cost of almost $50M.  The list was based on criteria that support water quality and the Florida Department of Environmental Protection (FDEP) Basin Management Action Plan (BMAP) and Total Daily Maximum Load (TMDL) objectives for the St. Lucie Estuary.

 

Prioritized Projects:

 

                     North River Shores Phase II

                     Golden Gate

                     Old Palm City

                     Beau Rivage

                     Gaines Avenue

                     Hibiscus Park

 

Martin County has historically utilized assessments to complete septic to sewer conversions and the cost to residents has varied depending on the availability of grant funding.  Projects being directly tied to the availability of grand funds does not allow for a timely sewer conversion program.  In order to achieve financial and project efficiencies, and avoid the limitations that grant reliance places on the projects, $4M in annual funding is required.  The following financial program structure will support consistent and predictable project implementation.

 

Large Sewer Projects - service to 300 or more residences

 

                     The Utilities and Solid Waste Department and the Public Works Department will contribute $2M annually from capital funds and franchise fees.

                     $2M in dedicated funding included in Capital Improvement Plan from other source(s) - to be determined.

                     Continued pursuit of grant funding.

 

This approach would accommodate establishing a $12K ceiling per single family residential assessment. 

 

Martin County has identified approximately 10,300 ERC’s in the prioritized areas.  At our current rate of septic to sewer conversion it will take over 30 years to make county sewer services available in the prioritized areas.  In addition, the special assessment process is not cost effective for small projects (i.e., those serving less than 300 connections).  Staff is proposing the “Connect to Protect” grinder sewer system program to address the small neighborhoods projects.  Staff is proposing a goal of this program is to keep the individual cost under $12,000 per ERC which is the same goal for large projects.

 

This program will be administered by the Utilities and Solid Waste Department with help from the Public Works Department.  The installation of the backbone force mains in the streets is critical for sewer availability.   Also, some neighborhoods will require construction of water lines at the same time. A summary of the program is listed below.

 

Grinder Program - service to less than 300 residences

 

Under current financial constraints, the Utilities and Solid Waste Department anticipates being able to establish 50 service connections per year.

 

                     The Utilities and Solid Waste Department’s annual contribution of $250K to construct all backbone force main service lines.

                     Where available and at the customer’s request, the Utilities and Solid Waste Department would install the grinder pump and all appurtenances, including the septic tank abandonment, but the homeowner will be responsible for the electrical connection.

                     The total cost will not exceed $12K and the Utilities and Solid Waste Department will finance the project and provide a monthly payment plan, which will be added to the customer’s utility bill.  This offers an advantage over an assessment in that it avoids Tax Collector and other fees that could add 8.75% to the cost.

                     Does not rely on grants.

                     Does require coordination with the Public Works Department to maximize the impact and cost efficiency of the projects. 

                     Office of Community Development will pursue Community Development Block Grants (CDBG) and others for implementation of this program in the Community Redevelopment Areas (CRA).

 

Sewer Availability

 

County policy requires a letter to be issued to all customers when service is available.  The letter informs customers that they have 365 days, from the date of the letter, to connect to service.  However, no provision is made for non-compliance.

 

In order to provide an incentive for customers to connect to service, staff is proposing that customers not connected within 365 days be billed the Sewer Availability Charge (SAC), which is currently $17.95 per month.

 

If the County fully implements the large project and connect to protect program the County could connect approximately 700 homes per year.  This will result in addressing all the prioritized areas in approximately 15 years.

 

 

 

LEGAL SUFFICIENCY REVIEW:

 

To the extent this items contains legal issues; it has been reviewed for legal sufficiency, although this is primarily a matter of Board policy.

 

RECOMMENDED ACTION:

 

RECOMMENDATION

1.                     Move that the Board approve the Large Sewer program, as described.

2.                     Move that the Board direct staff to bring back dedicated funding ($2M) options for the Large Sewer Projects.

3.                     Move that the Board direct staff to bring back a program, supported in the Utilities and Solid Waste Capital Improvement Project (CIP), that will provide a backbone Grinder Sewer System to support up to 300 connections per year. 

4.                     Move that the Board approve the implementation of the base monthly (SAC) fee for those customers that do not connect within a year of service availability.

 

ALTERNATIVE RECOMMENDATIONS

Move that the Board provide further direction.

 

FISCAL IMPACT:

 

RECOMMENDATION

Staff will provide a detail fiscal impact with the FY20 Capital Improvement Plan.

                     


ALTERNATIVE RECOMMENDATIONS

None

 

DOCUMENT(S) REQUIRING ACTION:

Budget Transfer / Amendment                      Chair Letter                                                               Contract / Agreement

Grant / Application                                          Notice          Ordinance                     Resolution

Other: