Martin County

File #: 19-0660   
Type: Consent Status: Agenda Ready
In control: Board of County Commissioners
On agenda: 8/27/2019 Final action:
Title: REQUEST THAT THE COUNTY APPROVE THREE AGREEMENTS WITH FLORIDA POWER AND LIGHT COMPANY FOR THE ELECTRICAL UNDERGROUND CONVERSION FOR THE BRIDGE ROAD MAIN STREET PROJECT IN HOBE SOUND
Attachments: 1. FPL_1of3-County_ROW_Agreement_Underground.pdf, 2. FPL_2of3-Applicant_Installed_Agreement_Underground.pdf, 3. FPL_3of3-Underground_Facilities_Conversion_Agreement.pdf

PLACEMENT: Consent

TITLE:

title  

REQUEST THAT THE COUNTY APPROVE THREE AGREEMENTS WITH FLORIDA POWER AND LIGHT COMPANY FOR THE ELECTRICAL UNDERGROUND CONVERSION FOR THE BRIDGE ROAD MAIN STREET PROJECT IN HOBE SOUND

end

EXECUTIVE SUMMARY:

executive summary

The Community Redevelopment Agency (CRA) is requesting that Florida Power and Light Company (FPL) convert the overhead power lines to underground. This conversion requires the County to enter into three agreements with FPL.

body

DEPARTMENT: Administration                     

PREPARED BY:                      Name: Susan Kores                     

                     Title:                     Manager, Office of Community Development                     

REQUESTED BY: Susan Kores                                          

 

PRESET:     

PROCEDURES: None                     

 

BACKGROUND/RELATED STRATEGIC GOAL:

 

1.                     Agreements prepared by:                     FPL

 

2.                     Parties to the Agreements:                     FPL and Martin County

 

3.                     Purpose of the Agreements:                     Conversion of FPL utilities from overhead to underground

 

4.                     New/Renewal/Modified:                     New

 

5.                     Duration:                                                               Applicant-Installed Facilities Agreement for Underground

Conversions (WR #4787756) duration is until the conversion project is complete; the duration of the other two Agreements is for as long as FPL, its successors or assigns, operate the undergrounded facilities

 

6.                     Benefits to Martin County:                     Underground utilities provide greater above ground space for the

Bridge Road Main Street project improvements

 

7.                     Cost to Martin County:                                          $138,539 which is part of the Bridge Road Main Street Project

 

The Bridge Road Main Street project will promote economic development by providing new infrastructure, increased parking, new sidewalks, street lighting, and landscaping.  Staff is coordinating with FPL to underground the electric lines, and with South Martin Regional Utilities (SMRU) for installation of an upgraded water main.  This enhanced roadway design will increase vehicular and pedestrian safety, corridor walkability, and assist in future parcel redevelopment.  The agreements necessary to accomplish the electrical undergrounding are as follows:

 

1.                     City/County Right-of-Way Agreement for Underground Conversions (WR #4787756).  This document authorizes the use of the Right-of-Way (ROW) by FPL for the conversions.  It also requires the County to reimburse FPL for costs to relocate, locate, expose, protect, rearrange, adjust or support the Underground Facilities when such services are required by the County or agency under County control.

2.                     Applicant-Installed Facilities Agreement for Underground Conversions (WR #4787756).  This document authorizes the County to install all the underground conduit and concrete products for the conversion project.  This agreement allows the County to accelerate the project schedule.

3.                     Underground Facilities Conversion Agreement (NON-GAF).  This document establishes the cost for the underground conversion and provides the County with a Tier 3 Avoided Storm Restoration Cost (ASRC) of $10,809.00 credit toward the project.

 

ISSUES:

 

None

 

LEGAL SUFFICIENCY REVIEW:

 

This item has been reviewed for legal sufficiency to determine whether it is consistent with applicable law, has identified and addressed legal risks, and has developed strategies for legal defensibility.

 

RECOMMENDED ACTION:

 

RECOMMENDATION

Move that the Board approve the agreements with FPL for undergrounding of utilities associated with the Bridge Road Main Street Project and authorize the Chairman to execute the documents.

 

ALTERNATIVE RECOMMENDATIONS

Pull this item from the Consent Agenda and do not approve the agreement and keep the overhead power lines.

 

FISCAL IMPACT:

 

RECOMMENDATION

The project is funded through monies already approved and available within the Hobe Sound Bridge Road Main Street Capital Improvement Plan.

                     

Funding Source

County Funds

Non-County Funds

35024-1324-3306-559-CRA16

 

$138,539.00

 

 

 

 

 

 

Subtotal

 

 

Project Total

 


ALTERNATIVE RECOMMENDATIONS

None

 

DOCUMENT(S) REQUIRING ACTION:

Budget Transfer / Amendment                      Chair Letter                                                               Contract / Agreement

Grant / Application                                          Notice          Ordinance                     Resolution

Other:     

This document may be reproduced upon request in an alternative format by contacting the County ADA Coordinator (772) 320-3131, the County Administration Office (772) 288-5400, Florida Relay 711, or by completing our accessibility feedback form at www.martin.fl.us/accessibility-feedback <http://www.martin.fl.us/accessibility-feedback>.