Martin County

File #: 19-0803   
Type: Public Hearing Quasi Judicial Status: Passed
In control: Board of County Commissioners
On agenda: 8/27/2019 Final action: 8/27/2019
Title: CREATIVE LAND MANAGEMENT, MAJOR MASTER SITE PLAN, PHASING PLAN, PHASE 1 FINAL SITE PLAN (A040-015)
Attachments: 1. 1-2019_0710_A040-015_DRT_Staff_FINAL.pdf, 2. 2a-2019_0724_A040-015_RESO_MSP_APPR_Draft.pdf, 3. 2b-LegalDescr_MasterSitePlan.pdf, 4. 2c-MSP&PP_2019_0408_A040-015.pdf, 5. 3a-2019_0726_A040-015_RESO_FSP_APPR_Draft.pdf, 6. 3b-LegalDescr_Phase1_FSP.pdf, 7. 3c-Ph1_FSP_2019_0709_A040-015.pdf, 8. 4-Creative Land Management Land Dedication Resolution.pdf, 9. 5-Easement Release Agreement-FINAL 3-20-19.pdf, 10. 6a-2018_0511_A040-015_APP_excerpt.pdf, 11. 6b-2018-1005_A040-015_RESUB-BS.pdf, 12. 6c-2018_1005_A040-015_RESUB_BS_Ph1.pdf, 13. 6d-2018_1005_A040-015_RESUB_excerpt.pdf, 14. 6e-2019_0124_A040-015_RESUB_excerpt.pdf, 15. 6f-2019_0408_A040-015_RESUB_excerpt.pdf, 16. 6g-2019_0408_A040-015_RESUB_LandscapePlan.pdf, 17. 7-Disclosure Pages from 2019_0124_A040-015_RESUB.pdf, 18. 8-Stipulated Agreement 12-14-16.pdf, 19. 9-Amended Stipulation Agreement 03-20-19.pdf, 20. 10-UOT from stipulation 06-29-2017.pdf, 21. 11-A040-015_Draft Commitment for Restoration.pdf, 22. 12-2018_0329_A040-015_Noticing_Sign.pdf, 23. 13-2019_0625_A040-015_CertifiedPropertyOwnersList_excerpt.pdf, 24. 14-2019_0725_A040-015_NoticingLttrSurroundingOwners.pdf, 25. 15-2019_0725_A040-015_RESO_MSP_DENY_Draft.pdf, 26. 16-2019_0726_A040-015_RESO_FSP_DENY_Draft.pdf, 27. 17-2019_0730_A040-015_LegalAd_LPA_BCC_Affidavit.pdf
PLACEMENT: Public Hearings - Quasi-Judicial
TITLE:
title
CREATIVE LAND MANAGEMENT, MAJOR MASTER SITE PLAN, PHASING PLAN, PHASE 1 FINAL SITE PLAN (A040-015)
end
EXECUTIVE SUMMARY:
executive summary
Request by Creative Land Management, LLC, for approval of a major development, Master Site Plan, Phasing Plan, and Phase 1 Final Site Plan for the proposed filling of an existing approximately 51-acre lake to be completed in three (3) phases on approximately 121.92 acres located on the west side of I-95 approximately 1.5 miles south of the I-95/SW Martin highway interchange in Palm City. Fill material is proposed to consist of source separated clean roofing materials and clean concrete from demolition sites. Included in this application is a request for a Certificate of Public Facilities Reservation.
body
DEPARTMENT: Growth Management
PREPARED BY: Name: Paul Schilling
Title: Growth Management Deputy Director
REQUESTED BY: Creative Land Management, LLC, Owner; Melissa Corbett, Agent

PRESET:
PROCEDURES: Quasi-Judicial

BACKGROUND/RELATED STRATEGIC GOAL:

The existing approximately 51-acre lake was constructed via approval of a mining project by the Board of County Commissioners on March 8, 2005, via Resolution 05-3.16. The project site has a future land use designation of Agricultural and a zoning district of A-2, Agricultural District. It is located outside the Urban Services District and this application includes a request for deferral of public facilities reservation for the master site plan approval and the issuance of a certificate of public facilities reservation for the phase 1 final site plan. This application is classified as a major development and was heard before the Local Planning Agency (LPA) on August 15, 2019. The recommendations of the LPA will be provided by staff to the Board of County Commissioners via testimony at the public hearing scheduled before the Board on August 27, 2019.

The applicant is proposing to fill the entire ...

Click here for full text