EXECUTIVE SUMMARY:

executive summary

The Florida Department of Transportation (FDOT) is actively designing a $1.289 million landscape improvement project for Kanner Highway (SR-76) from SE Cove Road to SE Monterey Road. Construction is projected to begin in October of 2023.  FDOT has reached out to Martin County to determine interest in contributing funds for the installation and maintenance of the project.

body

DEPARTMENT: Public Works                     

PREPARED BY:                      Name: Todd Warren and Kylie Yanchula                     

                     Title:                     Vegetation Maintenance Manager and Field Operations Administrator                     

REQUESTED BY: Martin County Board of County Commissioners                                          

 

PRESET:     

PROCEDURES: None                     

 

BACKGROUND/RELATED STRATEGIC GOAL:

 

The Florida Department of Transportation is actively designing a $1.289 million landscape improvement project for Kanner Highway (SR-76) from SE Cove Road to SE Monterey Road.  Construction is projected to begin in October of 2023.  The landscape architecture firm for the project, Cotleur and Hearing, is currently working on the conceptual landscape design plans which were presented at the Metropolitan Planning Organization meeting on September 20th, 2021.  On September 28th, 2021 the Board of County Commissioners expressed interest in expediting the project timeline and the Chair submitted a letter to this end on October 1st, 2021.

 

The conceptual design presented at the MPO Board meeting assumed the highest level of landscaping aesthetic. The current FDOT budget would need to be supplemented by County contributions ($635,963.65) for this level of aesthetic to be achieved.  Alternatively, the County may contribute fewer funds and the landscaping design will be determined by the overall budget.  The landscape architect developed renderings and projected costs associated with a high, medium, and low level of aesthetic for the Board to consider.  Rough cost estimates for annual maintenance were developed using ArcGIS and the roadside landscape maintenance contract.

Upon selection of the desired County contribution amount, if any, FDOT will require a Letter of Commitment from the Board.  The desired funding level contribution must be provided to FDOT this fiscal year so the project can be designed accordingly.

 

ISSUES:

 

The financial obligation cannot be absorbed by the current Roadway MSTU budget. Staff will have to defer projects or take the funds out of general fund reserves, which would need to be replenished in next year’s budget.  

 

LEGAL SUFFICIENCY REVIEW:

 

None

 

RECOMMENDED ACTION:

 

RECOMMENDATION

1.                     Move that the Board provide direction to staff in terms of the desired level of aesthetic and contribution amounts.

 

2.                     Move that the Chair execute a Letter of Commitment for the contribution amount and future maintenance to the Florida Department of Transportation.

 

ALTERNATIVE RECOMMENDATIONS

Move that the Board provide direction to staff.

 

FISCAL IMPACT:

 

RECOMMENDATION

Move that the Board select the level of capital contribution toward the desired level aesthetic (High: $632,600, Medium: $402,900, or Low: $250,000).

 

Move that the Board accept maintenance responsibility for the project, for which the actual annual maintenance costs will be determined upon completion of the design (estimated at High: $65,834, Medium: $54,605, or Low: $33,803). County maintenance will not begin until 2 years after construction, so a budget request form will be brought to the board in the appropriate fiscal year (currently projected to be FY2025). 

                     

Funding Source

County Funds

Non-County Funds

Roads MSTU as indicated in fiscal impact recommendation based on the desired level of aesthetic and direction from the Board

$250,000 - $632,600

 

Roads MSTU as indicated in fiscal impact recommendation based on the desired level of aesthetic and direction from the Board

Estimated Range $33,803-$65,834 (projected in FY2025)

 

 

 

 

Subtotal

 

 

Project Total

 


ALTERNATIVE RECOMMENDATIONS

Move that the Board contributes no additional funds toward the FDOT project.

 

DOCUMENT(S) REQUIRING ACTION:

Budget Transfer / Amendment                      Chair Letter                                                               Contract / Agreement

Grant / Application                                          Notice          Ordinance                     Resolution

Other:     

This document may be reproduced upon request in an alternative format by contacting the County ADA Coordinator (772) 320-3131, the County Administration Office (772) 288-5400, Florida Relay 711, or by completing our accessibility feedback form at www.martin.fl.us/accessibility-feedback <http://www.martin.fl.us/accessibility-feedback>.