PLACEMENT: Departmental - Quasi-Judicial
TITLE:
title
REQUEST BY KL WATERSIDE, LLC FOR FINAL SITE PLAN APPROVAL FOR SOUTH FLORIDA GATEWAY PUD PLAT INFRASTRUCTURE PLAN (S265-002)
end
EXECUTIVE SUMMARY:
executive summary
This is a request for approval of the South Florida Gateway Planned Unit Development (PUD) plat infrastructure final site plan for an approximate 180-acre parcel which is part of a 500-acre parent tract owned by KL Waterside, LLC. The project is located on the west side of SW Kanner Highway approximately 3/4 of a mile south of SW 96th Street. The property has been used for agricultural purposes, has been cleared and has no wetlands or existing native habitat. Included is a request for a Certificate of Public Facilities Exemption.
body
DEPARTMENT: Growth Management
PREPARED BY: Name: Peter Walden, AICP
Title: Deputy Growth Management Director
REQUESTED BY: Lucido and Associates, Morris Crady, AICP
PRESET:
PROCEDURES: Quasi-Judicial
BACKGROUND/RELATED STRATEGIC GOAL:
The proposed plat infrastructure final site plan for the South Florida Gateway PUD will provide the basis for future industrial development by creating lots and the associated infrastructure to support the development. Access is proposed on SW Kanner Highway and water and waste water service will be provided by Martin County Utilities.
The South Florida Gateway PUD Zoning Agreement including the master site plan was approved on February 1, 2022. The project is part of a free standing urban service district.
The project has received expedited staff review due to the targeted industries proposed for the development.
A review of this application by the Local Planning Agency was not required pursuant to Section 10.5.F.9., LDR.
The following supporting items are attached:
Staff Report
Resolution to Approve
Final Site Plan
Approved Master Site Plan
Application Materials
Landscape Plans
Disclosure of Interest
Legal Description
Sign Certification
Draft Resolution to Deny
Staff PowerPoint
ISSUES:
None
LEGAL SUFFICIENCY REVIEW:
Because this request involves the application of a policy to a specific application and site, it is a quasi-judicial decision. Quasi-judicial proceedings must be conducted with more formality than a legislative proceeding. In quasi-judicial proceedings, parties are entitled - as a matter of due process - to cross-examine witnesses, present evidence, demand that witnesses testify under oath, and demand a decision based on a correct application of the law and competent substantial evidence in the record.
RECOMMENDED ACTION:
RECOMMENDATION
• Move that the Board receive and file the agenda item and its attachments including the staff report as Exhibit 1.
• Move that the Board approve the request for the South Florida Gateway PUD Plat Infrastructure Final Site Plan.
ALTERNATIVE RECOMMENDATIONS
None
FISCAL IMPACT:
RECOMMENDATION
The applicant has paid the $9,127.00 application fee and the $290.00 completeness fee.
ALTERNATIVE RECOMMENDATIONS
None
DOCUMENT(S) REQUIRING ACTION:
☐Budget Transfer / Amendment ☐ Chair Letter ☐Contract / Agreement
☐Grant / Application ☐Notice ☐Ordinance ☒Resolution
☐Other:
This document may be reproduced upon request in an alternative format by contacting the County ADA Coordinator (772) 320-3131, the County Administration Office (772) 288-5400, Florida Relay 711, or by completing our accessibility feedback form at www.martin.fl.us/accessibility-feedback <http://www.martin.fl.us/accessibility-feedback>.