Martin County

File #: 22-1029   
Type: Consent Status: Agenda Ready
In control: Board of County Commissioners
On agenda: 8/9/2022 Final action:
Title: ADOPTION OF A RESOLUTION ACCEPTING AND APPROVING FIVE (5) UTILITY EASEMENTS ALONG SW WILLOW LAKE TRAIL FOR THE CAPE LIVE OAK WATER AND SEWER EXTENSION PROJECT IN STUART
Attachments: 1. Location_Map.pdf, 2. Resolution.pdf, 3. Utility Easements.pdf
PLACEMENT: Consent
TITLE:
title
ADOPTION OF A RESOLUTION ACCEPTING AND APPROVING FIVE (5) UTILITY EASEMENTS ALONG SW WILLOW LAKE TRAIL FOR THE CAPE LIVE OAK WATER AND SEWER EXTENSION PROJECT IN STUART
end
EXECUTIVE SUMMARY:
executive summary
This is a request for the adoption of a Resolution accepting and approving five (5) Utility Easements from the property owners of the parcels identified along the westerly extension of SW Willow Lake Trail for the Cape Live Oak water and sewer extension project.
body
DEPARTMENT: Public Works
PREPARED BY: Name: Carla T. Segura, FRP
Title: Real Property Manager
REQUESTED BY: Samuel Amerson, Utilities and Solid Waste Director

PRESET:
PROCEDURES: None

BACKGROUND/RELATED STRATEGIC GOAL:

1. Utility Easement Prepared By: Martin County

2. Parties to the Easement: Property Owners, Grantor
(Pisano, Venezia, Brownie, Bowers and Deziel)
Martin County, Grantee

3. Purpose of the Easement: To construct water main and sewer force main extensions

4. New/Renewal/Modified: New

5. Duration: Perpetual

6. Benefits to Martin County: Addition of new easements into the County network

7. Cost to Martin County: Title work and recording fees to be paid by USD

The Real Property Division has confirmed ownership of each easement premises and provided Mortgage information where necessary.
Sec. 139.31 and 139.32, General Ordinances, Martin County Code requires that any conveyance of an interest in land to Martin County for any public purpose shall be accepted and approved by Resolution from the Board of County Commissioners of Martin County.

ISSUES:

None

LEGAL SUFFICIENCY REVIEW:

This item has been reviewed for legal sufficiency to determine whether it is consistent with applicable law, has identified and addressed legal risks, and has developed strategies for legal defensibility.

RECOMMENDED ACTION:

RECOMMENDATION
Move that the Board adopt the Resolution accepting and approving the five (5) Ut...

Click here for full text