File #: 23-0817   
Type: Departmental Quasi Judicial Status: Passed
In control: Board of County Commissioners
On agenda: 6/6/2023 Final action: 6/6/2023
Title: REQUEST FOR REVISED FINAL SITE PLAN APPROVAL FOR THE THREE LAKES PROJECT (B115-007)
Attachments: 1. 2023_0524_B115-007_Staff_Report_Final.pdf, 2. 2023_0502_B115-007_Revised_Final_Site_Plan.pdf, 3. 2023_0425_B115-007_Utility Waiver.pdf, 4. 2023_0525_B115-007_Resolution to Approve.pdf, 5. 2023_0425_B115-007_Application_Materials.pdf, 6. 2023_0425_B115-007_Approved_Final_Site_Plan.pdf, 7. 5.11.23 - Signed KB - Dsiclosure of Interest Affidavit - Three Lakes Golf Club, LLC.pdf, 8. 2023_0425_B115-007_Sign_Posting_Affidavit.pdf, 9. THREE LAKES GOLF CLUB.pdf, 10. 2023-0525_B115-007 Reso to Deny.pdf
PLACEMENT: Departmental - Quasi-Judicial
TITLE:
title
REQUEST FOR REVISED FINAL SITE PLAN APPROVAL FOR THE THREE LAKES PROJECT (B115-007)
end
EXECUTIVE SUMMARY:
executive summary
This is a request for a Revised Major Final Site Plan approval for the Three Lakes Project. Revisions include the addition of a golf clubhouse, 14 golf cottages and associated infrastructure to the approximately 1,216-acre site located on SW Kanner Highway, approximately 2.5 miles west of I-95 in Stuart. Included is a request for a waiver consistent with Policy 10.2A.8.9, Comprehensive Growth Management Plan, Martin County Code (CGMP) allowing an increase in the maximum cumulative flow of on-site wastewater treatment and disposal systems from 2,000 to 5,000 gallons per day (GPD). Included is a request for a Certificate of Public Facilities Reservation.
body
DEPARTMENT: Growth Management
PREPARED BY: Name: Peter Walden, AICP
Title: Deputy Growth Management Director
REQUESTED BY: Lucido and Associates, Morris A. Crady, AICP

PRESET:
PROCEDURES: Quasi-Judicial

BACKGROUND/RELATED STRATEGIC GOAL:

The Three Lakes Major Final Site Plan and Preserve Area Management Plan were approved by the Board of County Commissioners (BCC) on September 27, 2022. The project includes two 18-hole golf courses, practice facilities, maintenance facilities and the associated infrastructure on an approximately 1,216-acre site located on SW Kanner Highway, north of and adjacent to SW Bridge Road approximately 2.5 miles west of I-95 in Stuart.

The site was used as a private family retreat, tree farm and hunting preserve. There is existing native plant material that is being transplanted and repurposed on the site. Irrigation will be provided by water pumped from the C-44 canal to the onsite lake system.

A Utility Waiver is requested pursuant to Policy 10.2A.8.9, CGMP to allow additional on-site wastewater flows that exceed the maximum 2,000 GPD. The maximum allowed flows will not exceed 5,...