Skip to main content

Martin County

File #: 23-0573   
Type: Departmental Quasi Judicial Status: Passed
In control: Board of County Commissioners
On agenda: 3/21/2023 Final action: 3/21/2023
Title: REQUEST PLAT APPROVAL FOR THE WILLOUGHBY TOWNHOMES PUD PROJECT (W096-003)
Attachments: 1. 2023_0210_W096-003_Staff_Report_Final.pdf, 2. 2023_0220_W096-003_Plat.pdf, 3. 2023_0220_W096-003_Contract_EOPC.pdf, 4. 2023_0220_W096-003_Surety.pdf, 5. 2023_0220_W096-003_Resolution_Revised_Final_Plan.pdf, 6. 2023_0220_W096-003_Revised_Final_Site_Plan.pdf, 7. 2022_1117_W096-004_Stamped_FS.pdf, 8. 2022_0220_W096-003_Application_Materials.pdf, 9. 2023_0220_W096-003_Disclosure_of_Interest.pdf, 10. 20210_0826-W096-003_sign_certification.pdf, 11. 2023_0216_W096-003_Resolution_to_Deny.pdf, 12. 2023_0220_W096-003_Staff_Presentation.pdf
PLACEMENT: Departmental - Quasi-Judicial
TITLE:
title
REQUEST PLAT APPROVAL FOR THE WILLOUGHBY TOWNHOMES PUD PROJECT (W096-003)
end
EXECUTIVE SUMMARY:
executive summary
This is a request by Meritage Homes of Florida, Inc. for approval of a plat, consistent with the master/final site plan of a residential major development consisting of 117 townhome units and associated infrastructure on 18.37 acres, resulting in a gross residential density of 6.4 units per acre. The subject site is located on the NE corner at the intersection of SE Salerno Road and SE Willoughby Boulevard in Stuart. Included in this application is a request for a Certificate of Public Facilities Exemption.
body
DEPARTMENT: Growth Management
PREPARED BY: Name: Peter Walden
Title: Deputy Growth Management Director
REQUESTED BY: Lucido and Associates, Morris A. Crady, AICP

PRESET:
PROCEDURES: Quasi-Judicial

BACKGROUND/RELATED STRATEGIC GOAL:

The Willoughby Townhomes PUD Zoning Agreement and master site plan were approved on April 22, 2022.The final site plan for the Willoughby Townhomes project was approved on October 18, 2022.

The development proposes a primary access from SE Darling Street to the north and a proposed emergency and pedestrian access to the south along SE Salerno Road. The development is located within the Primary Urban Services District and will be serviced by Martin County Utilities for potable water and wastewater services.

As a result of the review of the plat application, minor technical adjustments were required to the previously approved final site plan for the project to ensure consistency with the plat in accordance with Section 10.5.F.6(e), Land Development Regulations (LDR), Martin County Code.

Pursuant to Section 10.5.F., LDR, a review of this application by the Local Planning Agency is not required.

The following supporting documents are attached:

Staff Report
Plat
Contract and EOPC
Surety
Resolution for Revised Final Site Plan
Revised Fin...

Click here for full text